Box Tunnel

From Wikishire
Jump to: navigation, search
Box Tunnel
Wiltshire
BoxTunnelWest.jpg
Western portal
Location
Location
Location: 51°25’17"N, 2°13’34"W
Structure
Length: 1 mile 1,460 yards
History
Built 1838-1841
Information
Operated by: Network Rail

Box Tunnel is a railway tunnel in Wiltshire, between Bath and Chippenham, dug through Box Hill, and is a significant structure on the Great Western Main Line (GWML). It was built between 1838-1841 for the Great Western Railway (GWR) under the direction of the railway's engineer Isambard Kingdom Brunel.

Description

The tunnel is 1 mile 1,460 yards in length, straight, and descends on a 1 in 100 gradient from the east.

Box Tunnel is to be electrified with catenary as part of the GWML electrification scheme.[1] In the summer of 2015 the track was lowered 2 ft to allow for the electrification.[2]

The west portal is Grade-II* listed[3] and the east portal is Grade-II listed.[4]

Geology

Proposed in the 1835 Great Western Railway Act, the construction of a tunnel through Box Hill was considered an impossible and dangerous engineering project due to its length and the difficult underlying strata. The rocks through which it passes are Great Oolite on top with fuller's earth, Inferior Oolite and Bridport Sand beneath, a combination with which tunnellers at the time were already familiar.

The Great Oolite limestone, known locally as Bath Stone, is easily worked and had been mined for construction purposes since Roman times, particularly during the 17th and 18th centuries when, extracted by the room and pillar method, it was used to build many of the buildings in Bath.[5]

To assess the strata more accurately, between 1836 and 1837 Brunel sank eight shafts at intervals through the hill along the projected alignment to establish the nature of the underlying rock.[6]

Construction

The GWR company selected two contractors from a tendering process. George Burge of Herne Bay was the major contractor,[6] responsible for 75% of overall tunnel length working from the west. He appointed Samuel Hansard Yockney as his engineer and manager.[7] The locally based Lewis and Brewer were responsible for the remainder, starting from the east.

Engineering drawing of the longitudinal cross-section of Box Tunnel

Construction began in December 1838, divided into six isolated sections. Access to each was via a 25-foot-diameter ventilation shaft which ranged in depth from 70 ft on the eastern end to 300 ft towards the western end.[6] All men, construction equipment, materials and 247,000 cu. yds of extract had to go in and come out of the shafts using steam powered winches. The shafts also functioned as the safety exits from the tunnel. Candles provided the only lighting and were consumed at the rate of one tonne per week, equalled by the weekly consumption of explosives. Due to the time period required to get men in and out of the workings, blasting occurred with the men inside the tunnel. This, plus the hazard of water influx exceeding the calculated volumes, led to most of the deaths of around 100 navvies (railway construction workers) who worked on the project. Additional pumping and drainage needed to be installed during and after construction.[6]

These considerable restrictions led to a delay in the completion of the tunnel so that by August 1839 only 40% of the required works were finished.[6] By summer 1840, the London Paddington to Faringdon Road section of the GWML was complete, as was the track from Bath to Bristol Temple Meads. In January 1841, Brunel agreed with Burge and Yockney to increase their workforce from 1,200 to 4,000 workers, resulting in the effective completion of the tunnel in April 1841.[6] When the two ends of the tunnel were joined underground, there was found to be less than two inches of error in their alignment.[6]

Opening

The tunnel opened to traffic on 30 June 1841 without ceremony. The navvies continued working on the tunnel's western portal—which Brunel had designed in a grand classical style— near Box, Wiltshire. The eastern portal, at Corsham, has a more modest brick face with rusticated stone.[6]

Geographical location

Brunel's birthday

It was first reported in 1842[8] that twice a year the sun shines through the tunnel. At some point it has been assumed that Brunel deliberately aligned the tunnel so that the rising sun is visible through it on his birthday each year, April 9. This is not the case. Actual dates on which the sun has been seen to be visible from the western portal are 5 April 1992 and 5 September 1985 (the time approximately 06:34 on both occasions).

Angus Buchanan (2002, p. 269) writes:

The alignment of the Box Tunnel has been the subject of serious discussion in the New Civil Engineer and elsewhere. I am grateful to my friend James Richard for making calculations which convinced me that the alignment on 9 April would permit the sun to be visible through the tunnel soon after dawn on a fine day.

On the other hand, it has been asserted that it is impossible to guarantee the effect on a particular calendar day, because the angle at which the sun rises on a given date varies slightly with the cycle of leap years.[9] However, the sun subtends an angle of about half a degree, which is more than the year-to-year variation and more than the field of view through the tunnel, so it quite possibly seems to fill the tunnel every year. It is also asserted that Brunel failed to account for atmospheric refraction, and the effect is visible a few days too early.[10]

Buchanan (p. 226) concludes:

…I have found no documentary evidence for the often-repeated story that Brunel aligned the Box Tunnel so that the rising sun shone through it on his birthday, even though careful examination shows that it could indeed do so, and it is certainly a good story.

A mathematical exploration of the possibility of the phenomenon occurring on Brunel's birthday has been undertaken by C.P. Atkins.[11] Atkins concludes that, taking atmospheric refraction into account:

…full illumination [of the tunnel profile] can occur on April 7 in three (non-Leap) years out of four, whereas in a Leap-Year this should occur on April 6. …partial illumination is not possible on April 8, let alone the significant April 9.

The author suggests that reports of the sun shining through Box Tunnel on April 9, or even on April 15 and 16, as reported by "the local head ganger … suggests some reflection effect and is, in itself, worthy of further investigation".

The sun rises in alignment to the entrance to Box Tunnel on 9 April 2017

On Sunday April 9, 2017 with fine weather and the railway closed for electrification work and station upgrades at Bath Spa a team from GWR tested the theory, finding that the sunrise did not shine fully through the tunnel,.[12] However images released at the time show that the sun is remarkably well aligned to the tunnel.[13]

In December 2016, Genealogists’ Magazine published an analysis confirming two previous analyses, that the sun does indeed shine through the tunnel, but a few days prior to Brunel's birthday. On the 6th of April through the 1830s, complete solar penetration occurred on three years out of four in the leap year cycle. The author of the article was able to show that the 6th of April was the birthday of Brunel's sister, Emma Joan Brunel, and that therefore the alignment on this day may have been deliberate.[14]

Defence use

East portal with the quarry entrance to Tunnel Quarry clearly visible on the right

The hill surrounding the tunnel had been extensively quarried from 1844, extracting Bath Stone.

In the run-up towards World War II there was a recognition of a need to provide secure storage for munitions across the UK. The proposal was to create three Central Ammunition Depots (CADs): one in the north (Longtown, Cumberland); one in the Midlands (Nesscliffe, Shropshire); and one in the South at Tunnel quarry, Monkton Farleigh and Eastlays Ridge.[15]

During the 1930s, Tunnel quarry was renovated by the Royal Engineers as one of the three major stockpiles. In November 1937 the GWR was contracted to build a 1,000-foot-long raised twin-loading platform at Shockerwick for Monkton Farleigh, plus two sidings branching off from the adjacent Bristol–London mainline just outside the eastern entrance to Box Tunnel. Thirty feet below and at right angles to this point, the War Office had built a narrow-gauge wagon-sorting yard. This led to a 1¼-mile tunnel, built by The Cementation Company, descending at a rate of 1 in 8½ to the Central Ammunition Depot housed in the former mine workings. The whole logistics operation was designed to cope with a maximum of 1,000 tons of ammunition a day.[16] A Royal Air Force station, RAF Box, was also established using one area of the tunnels.[16] Due to the heavy Bristol Blitz, in 1940 Alfred McAlpine developed a fallback aircraft engine factory for the Bristol Aeroplane Company (BAC), although it never went into production.[16] BAC did, however, use the facility to accommodate the company's experimental department, which was working on a new engine for bombers and the Bristol Beaufighter.[17]

The CAD closed at the end of hostilities, although it was kept in an operational condition until the 1950s. The sidings were then cleared, and not used again until the mid-1980s when a museum opened for short period on the site. Portions of the ammunition depot were variously redeveloped to house the Central Government War Headquarters, RAF No.1 Signal Unit, Controller Defence Communication Network and the Corsham Computer Centre.[16]

Today, only the computer centre remains, while the visible north end of the tunnel is sealed by concrete and rubble. The former CAD is used for secure commercial document storage.[16]

References

Notes

  1. Department for Transport (2009). Britain's transport infrastructure: Rail electrification. London: DfT Publications. p. 30. ISBN 978-1-84864-018-4. http://www.dft.gov.uk/pgr/rail/pi/rail-electrification.pdf. 
  2. "Box tunnel reopens after Network Rail electrification work". BBC. http://www.bbc.co.uk/news/uk-england-34112951. Retrieved 1 September 2015. 
  3. National Heritage List 1271441: West Portal of Box Tunnel
  4. National Heritage List 1271441: Box Tunnel East Portal (MLN19912)
  5. "Combe Down Stone Mines Land Stabilisation Project". BANES. Archived from the original on 17 January 2006. https://web.archive.org/web/20060117002821/http://www.bathnes.gov.uk/BathNES/councilinformation/areainformation/combedownstonemines/default.htm. Retrieved 13 July 2006. 
  6. 6.0 6.1 6.2 6.3 6.4 6.5 6.6 6.7 "Box Tunnel". Network Rail. http://www.networkrail.co.uk/VirtualArchive/box-tunnel/. Retrieved 2 March 2013. 
  7. "Samuel Hansard Yockney". GracesGuide.co.uk. http://www.gracesguide.co.uk/Samuel_Hansard_Yockney. Retrieved 2 March 2013. 
  8. "On Saturday last the Box Tunnel…". Bristol Mirror (England). 15 April 1842. http://www.britishnewspaperarchive.co.uk/viewer/bl/0001044/18420416/097/0008. Retrieved 10 April 2017. 
  9. Karlson (1999)
  10. Lushman (1999)
  11. Atkins, C.P.. "Box Railway Tunnel and I. K. Brunel's Birthday: A Theoretical Investigation". http://articles.adsabs.harvard.edu//full/1985JBAA...95..260A/0000260.000.html. Retrieved 15 Nov 2014. 
  12. http://www.bathchronicle.co.uk/did-brunel-design-the-box-tunnel-so-that-the-light-would-shine-through-at-sunrise-on-his-birthday/story-30258983-detail/story.html
  13. https://www.theguardian.com/technology/2017/apr/10/isambard-kingdom-brunel-birthday-box-tunnel-bath-sun
  14. "Isambard's Gift". http://www.mirlibooks.com/isambards-gift.html. Retrieved 2017-05-25. 
  15. "Corsham Tunnels — A brief guide". gov.uk. https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/324883/Corsham_Tunnel_version1.pdf. Retrieved 7 April 2015. 
  16. 16.0 16.1 16.2 16.3 16.4 "CAD Monkton Farleigh". subbrit.org.uk. http://www.subbrit.org.uk/sb-sites/sites/m/monkton_farleigh/index.shtml. Retrieved 11 February 2012. 
  17. Gray, Tony (1987). The Road to Success: Alfred McAlpine 1935 – 1985. Rainbird Publishing. 

Sources

Outside links

Commons-logo.svg
("Wikimedia Commons" has material
about Box Tunnel)