Chichester Canal

From Wikishire
Jump to navigation Jump to search
Southgate basin at the Chichester end of the canal

The Chichester Canal is a canal in the south-west of Sussex. Its course is essentially intact, and it is navigable apart for its middle section, running for four and a half miles from the sea at Birdham on Chichester Harbour to Chichester through two locks.

The canal was originally part of the Portsmouth and Arundel Canal, and as such was opened in 1822, having taken three years to build. The canal could take ships of up to 100 tons. Dimensions were limited to 85 feet long, 18 feet wide and a draft of up to 7 feet.[1] When the Chichester Basin was formed in the 1820s, workmen unearthed 300 denarii: Chichester's origin was as the Roman Noviomagus Reginorum.

Location

History

A map of the planned route of the canal from 1815

Planning, construction and early operation

Proposals for a canal linking Chichester directly to the sea go back as least as far as 1585 when an Act of Parliament was passed allowing a cut linking Chichester with the sea.[2] Further proposals were made in the early 19th century, with schemes being proposed in 1801, 1802, 1803 and 1811, but none of these came to pass and as a result the first link to the sea was via a branch of the Portsmouth and Arundel Canal opened in 1822.[2] In 1817 it had been decided that the section between Chichester and Chichester Harbour, unlike the rest of the canal, would be built large enough to carry boats of 100 tons.[2] Putting this into practice required a new act of parliament which was obtained in 1819.[3] In the same year the construction of the Chichester branch began.[4] In digging out of the basin a hoard of 300 denarii was found.[5] The section of the canal that would become the Chichester Canal was formally opened on 9 April 1822[6]

Chichester Canal by J.M.W. Turner

The Portsmouth and Arundel Canal was conceived as part of a bigger plan to provide a secure inland canal route from London to Portsmouth, but by the time the route was completed, the war with France had ended. With the reason for its construction removed, the canal was not a commercial success, and apart from the Chichester section, it had fallen into disuse by 1847.[7]

Under the ownership of the Corporation of Chichester

The canal was transferred to the Corporation of Chichester in 1892.[8] In November of that year the City Surveyor gave a figure of £1000 to put the canal back into full working order; key tasks were repair of locks, bridges and the removal of weeds and mud from the channel.[9] By 1898 only 704 tons of goods were carried – tolls for the year were £18.[10] The last recorded commercial traffic was in 1906 when a load of shingle was carried from the Harbour to the basin.[11] In the same year it was found that the swing bridge at Donnington and Birdham needed to be repaired or replaced. Westhampnett Rural District Council wanted to replace them with fixed bridges (which would have blocked the canal) but the Corporation of Chichester wanted to keep the canal open to traffic. By 1923 the Corporation appears to have accepted that there would be no further great loads; it authorised and funded fixed bridges.[9]

The canal was official open for trade until June 1928 before being formally abandoned.[11]

In 1932 the section of the canal between Cutfield Bridge and Salterns lock was reopened to allow yachts to be berthed there.[12] The open section was initially leased by D.S. Vernon but in 1934 he transferred it to the Chichester Yacht Company.[13]

Second World War

During the Second World War the canal towpath was made an anti-tank and anti-barge route by the 4th Infantry Division to mitigate against a German invasion. This entailed dismantling 4 swing bridges, diversion of some of the Lavant to raise the water by three feet (thus over the towpath) and a low dam above Cutfield bridge.[14][13] The partial diversion proved hard to control and the fluctuations damaged the canal and a houseboat;[13] argument as to the duty to compensate lasted until June 1947.[15]

Post war

In 1953 the canal and surrounding lands were sold to the Council for £7,500.[16] The council let plans be known to use part of the canal for road improvement, on opposition and with higher priority issues for funds, these never took place.[16] The section below Cutfield Bridge continued to be leased to the Chichester Yacht Company while the upper part of the canal was leased to Chichester Canal Angling Association.[16]

In January 1994 floodwaters in lower Chichester were diverted into the canal.[17]

As of 2009 the sea lock is in working order but the other lock is not, when the restoration was halted due to the presence of water voles.[18]

Points of interest

Outside links

("Wikimedia Commons" has material
about Chichester Canal)

References

  1. Heneghan 1958, p. 15
  2. 2.0 2.1 2.2 Henegan 1958, pp. 1–2
  3. Green 2006, p. 12
  4. Green 2006, p. 24
  5. Green 2006, p. 26
  6. Green 2006, p. 30
  7. Vine 1985
  8. Vine 2005, p. 153
  9. 9.0 9.1 Henegan 1958, p. 19
  10. Vine 2005, p. 155
  11. 11.0 11.1 Vine 2005, p. 161
  12. Hadfield 1969, p. 146
  13. 13.0 13.1 13.2 Green 2006, p. 65
  14. Vine 2005, p. 163
  15. Green 2006, pp. 65–70
  16. 16.0 16.1 16.2 Green 2006, pp. 73–74
  17. Chaudhary, Vivek (11 January 1994). "Sales boom helps trader overcome that sinking feeling". The Guardian (Manchester). 
  18. "Voles Halt Chichester Restoration". Waterways (226): 32. Winter 2009. 

Books

  • Green, Alan H.J (2006). The History of Chichester's Canal. Sussex Industrial Archaeology Society. ISBN 0-9512036-1-4. 
  • Hadfield, Charles (1969). The Canals of South and South East England. David and Charles. ISBN 0-7153-4693-8. 
  • Heneghan, F. D. (1958). The Chichester Canal. Chichester City Council. 
  • Vine, P.A.L (1985). West Sussex waterways. Middleton Press. ISBN 0-906520-24-X. 
  • Vine, P.A.L (2005). London's Lost Route to Portsmouth. Phillimore & Co. ISBN 1-86077-283-8.